Radisson Red Twickenham Stadium
150 guest rooms and large public areas including conferencing and banqueting suites.

SUMMARY
Key works included:
Full strip-out & refurb of bedrooms, ensuites, corridors & public areas
Full rewire, including servicing of existing plant
Logistically challenging central London locations with no external space
Programme designed with multiple floors overlapping to maintain continuity and efficiency
LOCATION
Twickenham Stadium
DURATION
35 weeks
VALUE
£6m